Projects

Alliant Energy - City of Grinnell

Alliant Energy - City of Grinnell

2.5 MW DC / 2 MW AC
System Size
Grinnell, Iowa
Location

Alliant Energy collaborated with four Grinnell, Iowa community partners to develop the 5 megawatt (MW) Grinnell Solar Park through their Customer-Hosted Renewables program, which allows businesses and communities to host solar farms or battery storage systems on their land in exchange for monthly lease payments.

The solar park is located on a former brownfield site on Grinnell's west side, where the partners collaborated with the Iowa Department of Natural Resources to restore the land. Native grasses were planted to control erosion, filter groundwater, and provide habitat for pollinators and birds.

The City of Grinnell subdivided this restored site and sold tracts to three other partners: Grinnell College, the Mayflower Community, and Ahrens Park. Each partner owns their portion of the land within a single fenced area and leases it to Alliant Energy, which built individual solar arrays for each participant.

Specifications

System Size: 2.5 MW DC / 2 MW AC

Modules: (9,264) Canadian Solar CS7N-685TB-AG

Inverters: (19) Solectria XGI 250kW @ 600V and (2) Solectria XGI 125kW 250kW @ 600V

Electrical Interconnection: 24.9 kV line

Racking & Mounting: ground-mounted fixed-tilt